Project status report template
Where the project stands and why, in a line, then what was done, what is next, and what you need from the reader.
Open in DocsFree, with no account. What you type stays in this browser. Saves as Word, OpenDocument or PDF.


The template in full
Everything in square brackets is for you to replace. The date fills in as the day you open it.
Project status report
Project: [name] | Period: [from] to [today’s date] | Prepared by: [name]
Overall: [On track, at risk, or off track], because [the one reason that matters most].
Summary
[Three sentences for someone who reads nothing else.]
Done this period
- [What was finished]
Planned for next period
- [What will be done]
Milestones
| Milestone | Due | Now expected | Status |
|---|---|---|---|
| [Milestone] | [date] | [date] | [On track] |
| [Milestone] | [date] | [date] | [At risk] |
Risks and issues
| What | Effect if it happens | What is being done | Owner |
|---|---|---|---|
| [Risk or issue] | [name] |
Decisions needed
[What you need from the reader, from whom, and by when. Say none if there are none.]
Filling it in
- Give the overall status one reason. “At risk, because the supplier has not confirmed the delivery date” is a report; “At risk” is a worry.
- Show milestones with both the original date and the date now expected, so drift is visible over several reports.
- Put decisions needed last and make each one a question someone can answer yes or no.
- Send it on the same day each week or month. A report that arrives when things are going well and goes quiet when they are not is read that way.
More templates
- Meeting agendaEach item with when it starts, who leads it, and whether it is for a decision, a discussion or information.Open in Docs
- Risk registerEach risk with an owner, a likelihood and impact from 1 to 5, the score and rating worked out, and the next review date.Open in Sheets
- Statement of workWhat will be delivered, how each delivery is accepted, what it costs and when, and how a change is agreed.Open in Docs